Milestone tracker

Only events you can verify.

Plenty of sites will sell you a proprietary “growth index” for Dholera. We won’t. An index you can’t audit is marketing wearing a lab coat. What we track instead: milestones that actually happened — or are officially targeted — each with a status and a source.

  1. Jan 2016Commissioned

    DICDL formed

    Centre–State special purpose vehicle established to develop the SIR.

  2. Apr 2022Operational

    Tata Power 300 MW solar Phase 1 online

  3. 2025Operational

    Activation Area trunk infrastructure crosses 95% complete

  4. Dec 2025Under construction

    Airport Phase 1 civil works complete

    Runway ready; calibration flights followed in early 2026. Airport is still pre-passenger-operations.

  5. Jan 2026LoI signed

    UAE signs Letter of Intent on Dholera

    Gujarat govt × UAE Ministry of Investment — airport, MRO, greenfield port, townships, rail & grid.

  6. Jan 2026MoU signed

    Adani × Embraer aircraft partnership signed

    Dholera's aviation zone reported as the proposed final-assembly-line site.

  7. 31 Mar 2026Operational

    Ahmedabad–Dholera Expressway inaugurated

  8. 13 May 2026Cabinet-approved

    ₹20,667 Cr semi-high-speed rail corridor approved

    Union Cabinet — 134 km at 220 kmph, India's first, targeted FY 2030–31.

  9. 2026MoU signed

    Data-centre wave: L&T Vyoma MoU, Adani & Tillman plans

    Viksit Gujarat DC Policy 2026–29; Dholera positioned as the world's largest data-centre city.

  10. Dec 2026Planned

    Tata fab trial production target

  11. Dec 2026Planned

    Airport passenger operations expected

  12. 2030Planned

    Solar park 5 GW target